City of North Royalton, Ohio

Road Construction Update City of North RoyaltonBack to Engineering Department




 


August 26, 2010

Royalton Road/W. 130th Street
Intersection Improvements

Paving to Begin on Royalton Road/130th Street
Intersection With Temporary Lane Closures

Paving will begin for Royalton Road/W. 130th Street intersection improvement project in The Cities of North Royalton and Strongsville for Friday, August 27th from 4:00 p.m. until Saturday morning, August 28, 2010. There will be temporary lane closures with posted detours. Delays, however, are to be expected.

The improvement of this intersection is scheduled for completion in September 2010.

For more information, questions or concerns, please contact the Public Information Department, Monday through Friday, 8:30 a.m. to 4:30 p.m. at (216) 348-3824.


August 16, 2010

Royalton Road/W. 130th Street
Intersection Improvements

FINAL PAVEMENT SCHEDULE

Beginning on August 19, 2010, Karvo Paving will begin milling the roadway pavement and placing a leveling course across the limits of the project.  This work is expected to occur on August 20, 2010, also.

ALL WORK TO BE COMPLETED FROM 7:30PM until 6:00AM THE FOLLOWING DAY.

  • The week of August 23, 2010 will involve Karvo Paving adjusting castings and structures in the roadway to final grade.  Lane closures are expected.

  • Beginning on August 27, 2010, Karvo Paving will begin placing the final pavement surface course along the project.  This will also be performed from 7:30PM until 6:00AM

  • All of this schedule is weather dependent.  Turning restrictions may be removed during these phases.

Note:  Traffic delays in the following areas (listed below) are envisioned.

Traffic will be altered on Royalton Road, W. 130th Street and Edgerton Road, and signal patterns will be altered for the duration of construction.

Questions regarding this improvement project should be directed to the Construction Department at the Cuyahoga County Engineer’s Office.

Messages will be received at (216) 348-3838


July 28, 2010

Royalton Road/W. 130th
Intersection Improvements

Phase 4 Improvements Are Under Way!

The Contractor is working on the 4th phase of construction.  Pavement has been placed on the newly constructed lanes, and the driveway aprons, sidewalks and cleanup are currently under way.  The Cuyahoga County Engineer’s Office has moved message boards further outside the construction limits to warn motorists of delays and to use alternate routes.

  • Two-way traffic will be maintained throughout the construction, but motorists should expect delays.

  • Phase 4 will be to reconstruct the southwest corner of the intersection (south side of Royalton Road and west side of W. 130th Street in Strongsville).  Traffic patterns will be shifted to the north on Royalton Road and to the east on W. 130th Street. 

  • During Phase 4, the following restrictions will be implemented on traffic movements:

No LEFT turn from northbound W. 130th Street allowed

No RIGHT turn from eastbound Royalton Road

The improvement is scheduled to be completed in September.  The $2.2 million project is being funded by the Ohio Public Works Commission, Cuyahoga County and the cities of North Royalton and Strongsville.


July 20, 2010

Royalton Road/W. 130th
 Street Intersection Improvements
(pdf document)

UPDATE!!!!
 

Phase 4 – Maintenance of Traffic

  • Roadway Improvements are scheduled to begin on Wednesday, July 21, 2010.

  • Includes the southwest quadrant of the intersection (W. 130th Street and Royalton Road).

  • Royalton Road traffic is shifted to the north, to allow 1 lane of traffic in each direction through the work zone.

  • W. 130th Street traffic is shifted to the east, to allow 1 lane of traffic in each direction through the work zone, north of Royalton Road.

  • Includes construction of pavement widening and replacement, including sidewalks and driveways, within the work zone.

Estimated time of completion of Phase 4 is Thursday,
August 12, 2010.

TURNING RESTRICTIONS
PHASE 4!!!!!!!!

No LEFT turn from northbound W. 130th Street

No RIGHT turn from eastbound Royalton Road


June 24, 2010
Royalton Road/W. 130th
Intersection Improvements

Phase 3 Improvements Are Under Way!

The Contractor is finishing up the second phase of construction.  Pavement has been placed on the newly constructed lane, and the driveway aprons, sidewalks and cleanup are currently under way.  The Cuyahoga County Engineer’s Office has moved message boards further outside the construction limits to warn motorists of delays and to use alternate routes.

Two-way traffic will be maintained throughout the construction, but motorists should expect delays.

Phase 3 will be to reconstruct the northwest corner of the intersection (north side of Royalton Road and west side of W. 130th Street in Strongsville) starting the week of June 21st, but traffic patterns may change as soon as Tuesday, June 22, 2010.  Traffic patterns will be shifted to the south on Royalton Road and to the east on W. 130th Street.  During Phase 3 there are NO turning restrictions.

The improvement is scheduled to be completed in September.  The $2.2 million project is being funded by the Ohio Public Works Commission, Cuyahoga County and the cities of North Royalton and Strongsville.


May 6, 2010
Royalton Road/W. 130th Intersection Improvements

Phase 1 Improvements Wrapping up!

The Contractor is finishing up the first phase of construction.  Pavement is scheduled for the new lane on May 7, 2010, and the driveway aprons and cleanup are scheduled for the week of May 10th.  The Cuyahoga County Engineer’s Office has moved message boards further outside the construction limits to warn motorists of delays and to use alternate routes.

Two-way traffic will be maintained throughout the construction, but motorists should expect delays.

Phase 2 will be to reconstruct the northeast corner of the intersection (north side of Royalton road and east side of W. 130th Street in North Royalton) starting the week of May 17th.  Traffic patterns will be shifted to the south on Royalton Road and to the west on W. 130th Street.  During Phase 2, the following restrictions will be implemented on traffic movements:

No LEFT turn from southbound W. 130th Street allowed

No RIGHT turn from westbound Royalton Road

The improvement is scheduled to be completed in September.  The $2.2 million project is being funded by the Ohio Public Works Commission, Cuyahoga County and the cities of North Royalton and Strongsville.


March 24, 2010
Royalton
Road/W. 130th Intersection Improvements

Traffic patterns to change at
Royalton Road /W. 130th Street

A temporary traffic zone for Phase 1 of the Royalton Road-West 130th Street improvement project will be set up on Tuesday, March 30th as construction begins in the southeast quadrant of the intersection. The Cuyahoga County Engineer’s Office will erect message boards directing traffic into the proper lanes.

Two-way traffic will be maintained throughout the construction, but motorists should expect delays.

The improvement is scheduled to be completed in September.

The $2.2 million project is being funded by the Ohio Public Works Commission, Cuyahoga County and the cities of North Royalton and Strongsville.


March 19, 2010
Royalton
Road/W. 130th Intersection Improvements

The County will be starting this project earlier than expected.  The contractor will begin layout of the construction zone for Phase 1 on Thursday, March 25, 2010 and continue on Friday, March 26, 2010 to set up the construction zone.  This is moving up the schedule by 1 week sooner than originally anticipated.


March 4, 2010
Royalton Road/W. 130th Intersection Improvements
(pdf document)


Phase 1 – Maintenance of Traffic

Tuesday, April 6, 2010:

Roadway Improvements are scheduled to begin

Includes the southeast quadrant of the intersection (W. 130th Street, Edgerton Road and Royalton Road).

Royalton Road traffic is shifted to the north, to allow 1 lane of traffic in each direction through the work zone.

W. 130th Street traffic is shifted to the west, to allow 1 lane of traffic in each direction through the work zone.

Edgerton Road traffic is shifted to the southwest, to allow 1 lane of traffic in each direction through the work zone.

Includes construction of pavement widening and replacement, including sidewalks and driveways, within the work zone.

Estimated time of completion of Phase 1 is Wednesday,
April 28, 2010.

Phase 2 – Maintenance of Traffic

Thursday, April 29, 2010:

Roadway Improvements are scheduled to begin

Includes the northeast quadrant of the intersection (W. 130th Street, Edgerton Road and Royalton Road).

Royalton Road traffic is shifted to the south, to allow 1 lane of traffic in each direction through the work zone.

W. 130th Street traffic is shifted to the west, to allow 1 lane of traffic in each direction through the work zone, north of Royalton Road.

Edgerton Road traffic is shifted to the northwest, to allow 1 lane of traffic in each direction through the work zone.

Includes construction of pavement widening and replacement, including sidewalks and driveways, within the work zone.

Estimated time of completion of Phase 2 is Sunday, May 23, 2010.

TURNING RESTRICTIONS – PHASE 2!!!!!!!!

1. No LEFT turn from southbound W. 130th Street

2. No RIGHT turn from westbound Royalton Road


ROYALTON ROAD/ WEST 130 TH STREET
INTERSECTION IMPROVEMENTS

NOTICE TO RESIDENTS
(pdf document)

 

The Cuyahoga County Engineer’s Office will improve the intersection of Royalton Road/W. 130th Street in the Cities of North Royalton & Strongsville. Construction will begin in October 2009.

Completion… The improvement of the Royalton Road/W. 130th Street intersection is scheduled for completion in September 2010.

Thank You… We appreciate your understanding of our efforts to improve the quality of this intersection. It is our goal to provide an orderly flow of traffic through the area.

Patience… As work progresses, please be patient when dealing with the inconveniences of construction. We regret the temporary effects this work will have on your community.

If you have any questions or concerns, you may contact the North Royalton Engineering Department at 440-582-3001.
 


Back to Engineering Department