Back
to Engineering Department
August 26, 2010
Royalton Road/W. 130th Street
Intersection Improvements
Paving to Begin on Royalton Road/130th Street
Intersection With Temporary Lane Closures
Paving will begin for Royalton
Road/W. 130th Street intersection improvement project in The Cities of
North Royalton and Strongsville for Friday, August 27th from 4:00 p.m.
until Saturday morning, August 28, 2010. There will be temporary
lane closures with posted detours. Delays, however, are to be expected.
The improvement of this intersection is
scheduled for completion in September 2010.
For more information, questions or
concerns, please contact the Public Information Department, Monday
through Friday, 8:30 a.m. to 4:30 p.m. at (216) 348-3824. |
August 16, 2010
Royalton Road/W. 130th Street
Intersection Improvements
FINAL PAVEMENT SCHEDULE
Beginning on
August 19, 2010, Karvo Paving will begin milling the roadway pavement
and placing a leveling course across the limits of the project. This
work is expected to occur on August 20, 2010, also.
ALL WORK TO BE
COMPLETED FROM 7:30PM until 6:00AM THE FOLLOWING DAY.
-
The week of
August 23, 2010 will involve Karvo Paving adjusting castings
and structures in the roadway to final grade. Lane closures are
expected.
-
Beginning on
August 27, 2010, Karvo Paving will begin placing the final
pavement surface course along the project. This will also be
performed from 7:30PM until 6:00AM
-
All of this schedule
is weather dependent. Turning restrictions may be removed during
these phases.
Note: Traffic delays in the following areas (listed
below) are envisioned.
Traffic will be altered on Royalton Road, W. 130th
Street and Edgerton Road, and signal patterns will be altered for the
duration of construction.
Questions regarding this improvement
project should be directed to the Construction Department at the
Cuyahoga County Engineer’s Office.
Messages will be received at (216)
348-3838 |
July 28, 2010
Royalton Road/W. 130th
Intersection Improvements
Phase 4 Improvements
Are Under Way!
The Contractor is
working on the 4th phase of construction. Pavement has been placed on
the newly constructed lanes, and the driveway aprons, sidewalks and
cleanup are currently under way. The Cuyahoga County Engineer’s Office
has moved message boards further outside the construction limits to warn
motorists of delays and to use alternate routes.
-
Two-way traffic
will be maintained throughout the construction, but motorists should
expect delays.
-
Phase 4 will be
to reconstruct the southwest corner of the intersection (south side of
Royalton Road and west side of W. 130th Street in
Strongsville). Traffic patterns will be shifted to the north on
Royalton Road and to the east on W. 130th Street.
-
During Phase 4,
the following restrictions will be implemented on traffic movements:
No LEFT turn from
northbound W. 130th Street allowed
No RIGHT turn from
eastbound Royalton Road
The improvement is
scheduled to be completed in September. The $2.2 million project
is being funded by the Ohio Public Works Commission, Cuyahoga County and
the cities of North Royalton and Strongsville.
July 20, 2010
Royalton Road/W. 130th
Street Intersection Improvements
(pdf
document)
UPDATE!!!!
Phase 4 – Maintenance of Traffic
-
Roadway Improvements
are scheduled to begin on Wednesday, July 21, 2010.
-
Includes the southwest
quadrant of the intersection (W. 130th Street and Royalton
Road).
-
Royalton Road traffic
is shifted to the north, to allow 1 lane of traffic in each direction
through the work zone.
-
W. 130th
Street traffic is shifted to the east, to allow 1 lane of traffic in
each direction through the work zone, north of Royalton Road.
-
Includes construction
of pavement widening and replacement, including sidewalks and driveways,
within the work zone.
Estimated time of
completion of Phase 4 is Thursday,
August 12, 2010.
TURNING
RESTRICTIONS
PHASE 4!!!!!!!!
No LEFT turn from
northbound W. 130th Street
No RIGHT turn from eastbound Royalton Road |
June 24, 2010
Royalton Road/W. 130th
Intersection Improvements
Phase 3 Improvements
Are Under Way!
The Contractor is
finishing up the second phase of construction. Pavement has been placed
on the newly constructed lane, and the driveway aprons, sidewalks and
cleanup are currently under way. The Cuyahoga County Engineer’s Office
has moved message boards further outside the construction limits to warn
motorists of delays and to use alternate routes.
Two-way traffic
will be maintained throughout the construction, but motorists should
expect delays.
Phase 3 will be to reconstruct the northwest corner of the intersection
(north side of Royalton Road and west side of W. 130th Street
in Strongsville) starting the week of June 21st, but traffic patterns
may change as soon as Tuesday, June 22, 2010. Traffic patterns will be
shifted to the south on Royalton Road and to the east on W. 130th
Street. During Phase 3 there are NO turning restrictions.
The improvement is
scheduled to be completed in September. The $2.2 million project is
being funded by the Ohio Public Works Commission, Cuyahoga County and
the cities of North Royalton and Strongsville. |
May 6, 2010
Royalton Road/W. 130th Intersection Improvements
Phase 1 Improvements Wrapping up!
The Contractor is
finishing up the first phase of construction. Pavement is scheduled for
the new lane on May 7, 2010, and the driveway aprons and cleanup are
scheduled for the week of May 10th. The Cuyahoga County
Engineer’s Office has moved message boards further outside the
construction limits to warn motorists of delays and to use alternate
routes.
Two-way traffic
will be maintained throughout the construction, but motorists should
expect delays.
Phase 2 will be to
reconstruct the northeast corner of the intersection (north side of
Royalton road and east side of W. 130th Street in North
Royalton) starting the week of May 17th. Traffic patterns
will be shifted to the south on Royalton Road and to the west on W. 130th
Street. During Phase 2, the following restrictions will be implemented
on traffic movements:
No LEFT turn from
southbound W. 130th Street allowed
No RIGHT turn from
westbound Royalton Road
The improvement is
scheduled to be completed in September. The $2.2 million project is
being funded by the Ohio Public Works Commission, Cuyahoga County and
the cities of North Royalton and Strongsville. |
March 24, 2010
Royalton
Road/W. 130th Intersection Improvements
Traffic patterns to change at
Royalton Road /W. 130th Street
A temporary traffic zone for Phase 1 of the
Royalton Road-West 130th Street improvement project will be
set up on Tuesday, March 30th as construction begins in the
southeast quadrant of the intersection. The Cuyahoga County Engineer’s
Office will erect message boards directing traffic into the proper
lanes.
Two-way traffic will be maintained throughout the
construction, but motorists should expect delays.
The improvement is scheduled to be completed in
September.
The $2.2 million project is being funded by the Ohio
Public Works Commission, Cuyahoga County and the cities of North
Royalton and Strongsville.
|
March 19, 2010
Royalton
Road/W. 130th Intersection Improvements
The County will be starting this project earlier than
expected. The contractor will begin layout of the construction zone
for Phase 1 on Thursday, March 25, 2010 and continue on Friday, March
26, 2010 to set up the construction zone. This is moving up the
schedule by 1 week sooner than originally anticipated.
|
March 4, 2010
Royalton Road/W. 130th Intersection Improvements
(pdf
document) |
|
Phase 1 – Maintenance of Traffic
Tuesday, April 6, 2010:
Roadway Improvements are scheduled to begin
•
Includes the southeast quadrant of the
intersection (W. 130th Street, Edgerton Road and Royalton Road).
•
Royalton Road traffic is shifted to the
north, to allow 1 lane of traffic in each direction through the work
zone.
•
W. 130th Street traffic is shifted to the
west, to allow 1 lane of traffic in each direction through the work
zone.
•
Edgerton Road traffic is shifted to the
southwest, to allow 1 lane of traffic in each direction through the work
zone.
•
Includes construction of pavement widening
and replacement, including sidewalks and driveways, within the work
zone.
• Estimated time of completion of
Phase 1 is Wednesday,
April 28, 2010.
Phase 2 – Maintenance of Traffic
Thursday, April 29, 2010:
Roadway Improvements are scheduled to
begin
•
Includes the northeast quadrant of the
intersection (W. 130th Street, Edgerton Road and Royalton Road).
•
Royalton Road traffic is shifted to the
south, to allow 1 lane of traffic in each direction through the work
zone.
•
W. 130th Street traffic is shifted to the
west, to allow 1 lane of traffic in each direction through the work
zone, north of Royalton Road.
•
Edgerton Road traffic is shifted to the
northwest, to allow 1 lane of traffic in each direction through the work
zone.
• Includes
construction of pavement widening and replacement, including sidewalks
and driveways, within the work zone.
• Estimated time of completion of
Phase 2 is Sunday, May 23, 2010.
TURNING RESTRICTIONS – PHASE
2!!!!!!!!
1. No LEFT turn from
southbound W. 130th Street
2. No RIGHT turn from
westbound Royalton Road
|
|
ROYALTON ROAD/ WEST 130 TH
STREET
INTERSECTION IMPROVEMENTS
NOTICE TO RESIDENTS
(pdf
document)
The Cuyahoga County Engineer’s Office will improve the
intersection of Royalton Road/W. 130th Street in the Cities of North
Royalton & Strongsville. Construction will begin in October 2009.
Completion… The improvement of the Royalton Road/W.
130th Street intersection is scheduled for completion in September 2010.
Thank You… We appreciate your understanding of our
efforts to improve the quality of this intersection. It is our goal to
provide an orderly flow of traffic through the area.
Patience… As work progresses, please be patient when
dealing with the inconveniences of construction. We regret the temporary
effects this work will have on your community.
If you have any questions or concerns, you may
contact the North Royalton Engineering Department at 440-582-3001.
|
|
Back to
Engineering Department |
|
|
|